MODULE 8 ACTIVITY #16 SHORT INTERVAL SCHEDULE

MODULE 8 ACTIVITY #16 SHORT INTERVAL SCHEDULE

Due: Sat May 9, 2026 11:59pm

Ungraded, 10 Possible Points10 Points Possible

In Progress

NEXT UP: Submit Assignment

Unlimited Attempts Allowed

This activity is designed to teach you how to create a short interval schedule in Microsoft Excel. Please download the Activity #16 Starter File and follow the instructions below.

Background:

Your Project Manager wants you to create a 3 Week look ahead schedule. Knowing that the activity “Building Foundation Formwork” was completed yesterday, this gives you a starting activity and starting date.

Task:

3 Week Look Ahead Schedule, follow the steps below:

-Remember the point of a short interval schedule, is to add more detail

-Examples of more detail may include:

-Number of labors needed

-Materials to be ordered and / or delivered

-Equipment to be installed

-Equipment necessary for construction

-Inspections

-Safety concerns

-Important meetings

-Your schedule will encompass +/- (15) activities, therefor (45) description rows have been provided on the starter file

-All (45) rows must be used at a minimum, but feel free to add more

Delivery Method:

Include your name in the cells above and the Activity Number: Activity #16

Upload the Excel file when completed

Save your files as: ACT16_Lastname

Refer to the video below:

Result:

Once completed you should have 3 Week Look Ahead Schedule.

Submitting your Assignment

  1. Find the “Choose a submission type” section at the bottom of this assignment page (if this section is not displayed, the submission type has been chosen for you). Choose your submission type from the options listed there.
  2. Complete the assignment for the chosen Submission Type.
  3. Click the Submit Assignment button to submit.

or contact your instructor if you need assistance.

BCOM 220 ACTIVITY #16

BCOM 220 ACTIVITY #16
Criteria Ratings Points

File name

1 pts

0 pts

/1 pts

Schedule begins with correct activity for students schedule and correct date

2.5 pts

0 pts

/2.5 pts

Additional detail added where appropriate (should be minimum 45 rows)

3 pts

0 pts

/3 pts

Schedule formatted appropriately

2.5 pts

0 pts

/2.5 pts

Submission of XLS file

1 pts

0 pts

/1 pts