2 Part assignment. Part 1 is the attached two questions. Part is listed below:
Prompt: As a continuation of the case study in this week’s assignment, consider this new scenario.
The project plan called for the development of 500 code modules and allowed five weeks of schedule time to do it. At the end of the five-week period, you assess the progress only to find that 50 modules did not pass code inspection and now need revision.
Discuss how this will affect your project schedule. Also, what might a project manager have done to catch this problem before it arose?