Draw the activity on node network for the following project activities:
Activity Duration IPA
A 5days
B 3days A
C 4days A
D 5days A
E 2days B
F 3days B, C
G 2days D, E,F
Please submit your completed assignment using a format thatadequately captures your hand-drawn network to the Week 1 weekly Assignmentlink. If you do not wish to submit a hand-drawn network diagram, you may usesoftware to draw the diagram.